A 20MW facility is being constructed off the Cornish coast to allow the full scale testing of up to four different wave power machines
.
Addressing a conference session at the Oceanology International event at London’s ExCel centre, Nick Harrington, who works for the South West of England Regional Development Agency said that the facility is being set up just to the North East of St Ives, taking the power ashore where there used to be a coal fired power station.
The facility will include four sub sea transformers to step up the 11kV generated by the wave power generators to 33kV for onward transmission. Planning permission was finally granted on September 17th 2007, and the first three participants are expected to be Pelamis Wave Power with their wave riding generator, ORECon, with its oscillating water columns and ‘Multi Resonant Chambers’ and Ocean Power Technologies with its oscillating ‘PowerBuoys’. He said there was, “Already a waiting list of two or three”.
|
|
| |
Author Tom Shelley
|
| |
| |
|
| |
This material is protected by Findlay Media copyright 2009. See Terms and Conditions. One-off usage is permitted but bulk copying is not. For multiple copies contact the sales team.
|
| |
|
|
| |
To comment on news stories or blogs you need to complete our 60 second registration process. Once completed this then allows you to download any and all white papers, register for e-zines and access our detailed supplier directory for FREE.
If you are all ready a registered user then enter your e-mail address and login.
You will need to have logged in prior to entering your comments in the boxes provided.
|