02/07/2008
Email to a friend
Comment on this article
|
The transformer station attached to the 1.2 MW SeaGen marine current generator in Strangford Narrows, Northern Ireland is scheduled to go live today. July 2nd 2008, with first production of electric power to start on Friday July 4th
.
Installation was delayed by lack of a suitable rig to install the cylindrical pile on which the two 16m rotors are mounted. This led to a last minute redesign to mount the main support on a 9m x 17m quadrupole base with pin piles so the construction could be lowered into position by a crane barge.
Angela Robotham, engineering director of designers and builders, Marine Current Turbines said that because all available drilling and pile installation rigs are fully engaged in installing offshore wind turbines, their engineering team is looking at, “All possible support mechanisms, including monopiles, tripods and quadrupoles”, for subsequent installations, such as the next project, which is to be a 10.5 MW tidal energy farm off the coast of the Welsh island of Anglesey in a patch of 25 metre deep open sea known as The Skerries. Robotham considers that marine current technology is, “Where the wind turbine industry was 30 years ago”.
The SeaGen was designed using Autodesk Inventor
|
|
| |
Author Tom Shelley
|
| |
| |
|
| |
This material is protected by Findlay Media copyright 2012. See Terms and Conditions. One-off usage is permitted but bulk copying is not. For multiple copies contact the sales team.
|
| |
|
|
| |
To comment on news stories or blogs you need to complete our 60 second registration
process. Once completed this then allows you to download any and all white papers,
register for e-zines and access our detailed supplier directory for FREE.
If you are all ready a registered user then enter your e-mail address and login.
You will need to have logged in prior to entering your comments in the boxes provided.
|